The 'effect' in a cause-and-effect diagram refers to:
Show answer & explanation

Correct answer: The problem or outcome being investigated

Explanation

In a fishbone (cause-and-effect) diagram, the 'effect' is the problem or outcome being analyzed — it is written at the head (right side) of the fish skeleton. The 'bones' represent potential categories of causes contributing to that effect.

**Why not A:** The corrective action is a response developed after the causes are identified, not the effect itself. The effect is the starting point of the analysis, while corrective actions are outcomes of the investigation that address the identified causes.

**Why not B:** The solution being implemented is a result of the analysis process, not the effect being investigated. In a cause-and-effect diagram, the effect is the problem statement, and solutions are developed after causes have been identified and analyzed.

**Why not C:** The team member responsible for the issue is not the effect in a cause-and-effect diagram. The effect is the problem or outcome being studied. Individual responsibility may be explored as a potential contributing cause, but it is not the central problem being analyzed.

Key Concept

This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).