CAPM Practice: Demonstrate an understanding of common problem-solving tools and techniques
Question 85 of 105 in Demonstrate an understanding of common problem-solving tools and techniques
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Installation Error
Explanation
Counting the tallies: Installation Error = 12, Measurement Error = 4, Documentation Error = 10. Installation Errors occur most frequently. This raw data from the check sheet would often be transferred to a Pareto chart to visually prioritize improvement efforts.
**Why not A:** Documentation Errors have a tally of 10, which is fewer than the 12 Installation Errors. While Documentation Errors are the second most frequent defect type, they are not the most frequent.
**Why not C:** The three defect types have different frequencies: Installation Error (12), Documentation Error (10), and Measurement Error (4). They are clearly not equally frequent, as the tallies show distinct counts for each category.
**Why not D:** Measurement Errors have only 4 tallies, making them the least frequent defect type of the three categories. This is significantly fewer than both Installation Errors (12) and Documentation Errors (10).
Key Concept
This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).