CAPM Practice: Demonstrate an understanding of common problem-solving tools and techniques

Question 99 of 105 in Demonstrate an understanding of common problem-solving tools and techniques

Pick an answer below — you'll get the explanation instantly, no signup.

A project manager finds that a team member's error caused a deliverable defect. Instead of blaming the individual, the project manager asks 'why' five times and discovers an unclear work instruction was the real cause. This approach reflects which problem-solving principle?
Show answer & explanation

Correct answer: Focus on root causes rather than symptoms or blame

Explanation

Effective root cause analysis focuses on systemic causes rather than individual blame. Finding that an unclear work instruction caused the error identifies a process improvement opportunity that will prevent future recurrence — far more effective than disciplining the individual for a system failure.

**Why not A:** Individual performance management focuses on evaluating and managing a person's work output. The scenario demonstrates that the root cause was a systemic issue (unclear work instruction), not an individual performance problem, making this approach counterproductive.

**Why not C:** Escalation to HR for policy violations is punitive and misses the point. The defect was caused by an unclear work instruction, which is a process failure. HR escalation would blame the individual for a system-level problem.

**Why not D:** Accountability over process improvement prioritizes assigning blame rather than fixing the underlying cause. The 5 Whys revealed that the unclear work instruction was the real issue, making process improvement the appropriate response rather than holding an individual accountable for a systemic failure.

Key Concept

This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).