CAPM Practice: Demonstrate an understanding of common problem-solving tools and techniques
Question 28 of 105 in Demonstrate an understanding of common problem-solving tools and techniques
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: 1. Brainstorming → Generate creative ideas without immediate criticism 2. Daily standup meeting → Provide quick team coordination and identify blockers 3. Focus group → Gather qualitative feedback from selected stakeholders 4. Root cause analysis → Identify underlying causes of a problem or defect
Explanation
Brainstorming generates ideas freely without judgment. Daily standup meetings (often 15 minutes) enable quick team synchronization and surface impediments. Focus groups gather qualitative opinions from specific stakeholder groups. Root cause analysis uses techniques like fishbone diagrams or 5 Whys to identify underlying problem causes.
**Why not A:** This option mismatches brainstorming with qualitative stakeholder feedback and focus groups with idea generation. Brainstorming generates creative ideas without criticism, while focus groups gather targeted qualitative feedback from selected participants.
**Why not B:** This option correctly matches standup meetings and focus groups but swaps brainstorming with root cause analysis, assigning root cause identification to brainstorming and idea generation to root cause analysis. Brainstorming is for idea generation, and root cause analysis identifies underlying causes.
**Why not C:** This option assigns team coordination to brainstorming and qualitative feedback to standup meetings, reversing their purposes. Standup meetings are brief synchronization events, while brainstorming is for creative idea generation.
Key Concept
This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).