A project manager facilitates a lessons learned session at project close. Some team members resist sharing negative experiences due to fear of blame. What approach BEST addresses this challenge?
Show answer & explanation

Correct answer: Establish psychological safety by framing the session as process improvement, not blame assignment

Explanation

Psychological safety is essential for honest lessons learned sessions. By explicitly framing the discussion as process improvement rather than individual blame, the facilitator creates an environment where team members feel safe sharing failures, mistakes, and suggestions — which is where the most valuable organizational learning occurs.

**Why not A:** Making attendance optional would likely reduce participation and limit the diversity of perspectives captured. Lessons learned sessions are most valuable when all team members contribute their experiences, and optional attendance undermines this goal.

**Why not B:** Focusing exclusively on positive lessons avoids the most valuable organizational learning opportunities. Understanding what went wrong and why is essential for continuous improvement. Excluding negative experiences produces an incomplete and less useful record.

**Why not C:** Having the project sponsor lead the session may actually increase fear of blame, as team members might be less candid with a senior authority figure present. The key is establishing psychological safety through framing, not changing the facilitator to someone with more organizational power.

Key Concept

This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).