CAPM Practice: Demonstrate an understanding of common problem-solving tools and techniques
Question 93 of 105 in Demonstrate an understanding of common problem-solving tools and techniques
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Issue description, owner, priority, target resolution date, and status
Explanation
An issue log entry should capture: what the issue is (description), who is responsible for resolving it (owner), how urgent/important it is (priority), when it should be resolved (target resolution date), and where it stands (status). This information ensures issues are tracked, owned, and resolved systematically.
**Why not B:** Change request number, change type, and approval status are elements of a change log or change request form, not an issue log. Issue logs track problems that need resolution, while change logs track proposed modifications to the project.
**Why not C:** Risk probability, risk impact, and risk response strategy are elements of a risk register. The risk register is a separate document from the issue log, tracking uncertain future events rather than current problems requiring resolution.
**Why not D:** Lesson learned, recommendation, and implementation date are elements of a lessons learned register. Lessons learned capture knowledge for future improvement, while issue logs focus on tracking and resolving current project problems.
Key Concept
This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).