CAPM Practice: Demonstrate an understanding of business analysis (BA) roles and responsibilities
Question 1 of 67 in Demonstrate an understanding of business analysis (BA) roles and responsibilities
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Bridging the gap between business stakeholders and technical teams by eliciting, analyzing, and communicating requirements
Explanation
A business analyst serves as the bridge between business needs and technical solutions — eliciting requirements from stakeholders, analyzing their feasibility, and communicating them clearly to the development team.
**Why not A:** Managing the project schedule and budget is the project manager's primary responsibility, not the BA's. While BAs may provide input on schedule estimates for requirements activities, overall project schedule and budget management belongs to the PM role.
**Why not B:** Writing code and building software solutions is the responsibility of the development team. The BA focuses on understanding and communicating what needs to be built, not on the technical implementation. BAs define requirements; developers implement them.
**Why not D:** Overseeing team performance and conducting performance reviews is a management or HR function. The BA role is focused on requirements-related activities such as elicitation, analysis, and stakeholder communication, not on managing team members' performance or conducting evaluations.
Key Concept
This question covers Demonstrate an understanding of business analysis (BA) roles and responsibilities under Demonstrate an understanding of business analysis (BA) roles and responsibilities (Business Analysis Frameworks).