CAPM Practice: Demonstrate an understanding of business analysis (BA) roles and responsibilities
Question 16 of 67 in Demonstrate an understanding of business analysis (BA) roles and responsibilities
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Solution scope defines the features and functions of the product; project scope defines all the work needed to deliver the solution (including BA, PM, testing work)
Explanation
Solution scope describes what the product does (features, capabilities). Project scope describes all work required to deliver the project — including analysis, design, testing, training, and rollout. BAs primarily define solution scope.
**Why not B:** Solution scope and project scope are distinct concepts that should not be used interchangeably. Conflating them leads to confusion about what the product must do versus what work the project team must perform. The BABOK and PMBOK both recognize these as separate concepts with different owners and management approaches.
**Why not C:** This mischaracterizes both concepts. Solution scope defines product features and capabilities, not budget. Project scope encompasses all work required to deliver the solution, including project management work such as cost planning, but the budget itself is not part of either scope — it is managed separately through the cost baseline.
**Why not D:** While project scope is broader than solution scope, characterizing solution scope as limited to software features is inaccurate. Solution scope encompasses all features and functions of the delivered product, which may include hardware, processes, training, organizational changes, and other non-software components depending on the nature of the solution.
Key Concept
This question covers Demonstrate an understanding of business analysis (BA) roles and responsibilities under Demonstrate an understanding of business analysis (BA) roles and responsibilities (Business Analysis Frameworks).