Question 3 of 67 in Demonstrate an understanding of business analysis (BA) roles and responsibilities

Pick an answer below — you'll get the explanation instantly, no signup.

What is the difference between a 'business need' and a 'requirement' in business analysis?
Show answer & explanation

Correct answer: A business need is the problem or opportunity being addressed; a requirement is a specific condition the solution must meet to address that need

Explanation

A business need describes the problem or opportunity (e.g., 'We're losing customers due to slow checkout'). Requirements describe the conditions the solution must satisfy (e.g., 'Checkout must complete in under 30 seconds'). BA bridges these layers.

**Why not A:** Ownership of business needs and requirements is not defined by role in this way. Business analysts, stakeholders, and subject matter experts all contribute to documenting both needs and requirements. The distinction is about abstraction level, not who writes them.

**Why not C:** Business needs and requirements are not the same thing. A business need identifies the high-level problem or opportunity, while a requirement specifies a detailed condition the solution must satisfy. Conflating them leads to poorly scoped solutions.

**Why not D:** This reverses the actual relationship. Business needs are business-facing, describing organizational problems or opportunities. Requirements can be either business-facing (functional) or technical (non-functional), depending on their nature.

Key Concept

This question covers Demonstrate an understanding of business analysis (BA) roles and responsibilities under Demonstrate an understanding of business analysis (BA) roles and responsibilities (Business Analysis Frameworks).