CAPM Practice: Demonstrate an understanding of a project management plan schedule
Question 7 of 85 in Demonstrate an understanding of a project management plan schedule
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: A significant event or point in time that marks a key achievement or decision
Explanation
A milestone represents a significant event — such as project phase completion, major deliverable acceptance, regulatory approval, or a key decision point. Milestones have zero duration; they mark a point in time, not a period of work. They are used to track progress against key objectives.
**Why not A:** A work package requiring specialized resources describes a component of the WBS, not a milestone. Work packages involve actual effort and resource consumption, while milestones are zero-duration markers of significant events.
**Why not B:** While milestones have zero duration, describing them as tasks with zero float and zero resources is misleading. Milestones can have float (they are not necessarily on the critical path), and defining them by resource count mischaracterizes their purpose as significant markers of achievement.
**Why not C:** The longest activity on the critical path is simply a critical activity with the greatest duration. Milestones have zero duration by definition and represent points in time, not activities with measurable duration on the critical path.
Key Concept
This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).