CAPM Practice: Demonstrate an understanding of a project management plan schedule

A project manager identifies that an activity has a duration of 10 days, early start of day 15, late start of day 18, early finish of day 24, and late finish of day 27. What is the total float?

Key Concept

This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).