CAPM Practice: Demonstrate an understanding of a project management plan schedule

Question 15 of 85 in Demonstrate an understanding of a project management plan schedule

Pick an answer below — you'll get the explanation instantly, no signup.

A project manager identifies that an activity has a duration of 10 days, early start of day 15, late start of day 18, early finish of day 24, and late finish of day 27. What is the total float?
Show answer & explanation

Correct answer: 3 days

Explanation

Total float = Late Start - Early Start = 18 - 15 = 3 days (also = Late Finish - Early Finish = 27 - 24 = 3 days). This activity can be delayed up to 3 days without delaying the project end date. It has 3 days of schedule flexibility.

**Why not A:** Six days would require a Late Start of 21 or a Late Finish of 30, which contradicts the given values. The calculation LS - ES = 18 - 15 = 3 days, not 6 days.

**Why not C:** Ten days is the activity's duration, not its float. Float measures schedule flexibility (the difference between late and early dates), while duration measures how long the activity takes to complete.

**Why not D:** Zero days of float would mean the activity is on the critical path, but this activity has a 3-day difference between its late and early start dates (18 - 15 = 3), confirming it has schedule flexibility and is not on the critical path.

Key Concept

This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).