CAPM Practice: Demonstrate an understanding of a project management plan schedule
Question 54 of 85 in Demonstrate an understanding of a project management plan schedule
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The successor must wait 3 days after the predecessor finishes before it can start
Explanation
A positive lag in an FS dependency adds a waiting period. The successor activity cannot start until 3 days after the predecessor finishes. Common examples include waiting for concrete to cure, paint to dry, or approvals to be processed before the next activity can begin.
**Why not A:** Starting 3 days before the predecessor finishes describes a lead (negative lag), not a positive lag. A lead accelerates the schedule by allowing overlap, while a positive lag delays the start of the successor after the dependency condition is met.
**Why not C:** Three days of overlap between activities would describe a lead or negative lag in an FS relationship. A positive lag of 3 days creates a waiting period after the predecessor finishes, not an overlap during which both activities execute simultaneously.
**Why not D:** The predecessor finishing 3 days early is a schedule performance outcome, not a dependency definition. The lag defines a mandatory waiting period after the predecessor finishes, regardless of whether the predecessor finishes early or late.
Key Concept
This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).