CAPM Practice: Demonstrate an understanding of a project management plan schedule

Question 49 of 85 in Demonstrate an understanding of a project management plan schedule

Pick an answer below — you'll get the explanation instantly, no signup.

A resource calendar in project scheduling documents:
Show answer & explanation

Correct answer: When resources are available (working days, holidays, part-time availability)

Explanation

Resource calendars identify working and non-working days for project resources — including standard working hours, company holidays, vacations, and part-time availability. This information is essential for realistic schedule development because activities can only be worked during periods when resources are available.

**Why not B:** Milestone completion dates are documented in the project schedule and milestone list, not in resource calendars. Resource calendars track resource availability, not project milestone timing.

**Why not C:** The sequence of activities each resource performs is defined in the resource assignments and project schedule, not the resource calendar. The calendar shows when resources are available; the schedule shows what they will work on and in what order.

**Why not D:** The number of resources assigned to each work package is documented in resource assignments or the responsibility assignment matrix. Resource calendars address availability timing, not assignment quantities.

Key Concept

This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).