CAPM Practice: Demonstrate an understanding of a project management plan schedule

A project schedule shows that Activity A (5 days) → Activity B (3 days) → Activity C (4 days) is one path, and Activity D (7 days) → Activity E (5 days) is another path, both paths starting simultaneously and merging at the project end. What is the critical path duration?

Key Concept

This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).