CAPM Practice: Demonstrate an understanding of a project management plan schedule
Question 61 of 85 in Demonstrate an understanding of a project management plan schedule
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: 12 days — both paths are equal
Explanation
Path 1 (A→B→C) = 5 + 3 + 4 = 12 days. Path 2 (D→E) = 7 + 5 = 12 days. Both paths have equal duration of 12 days — both are critical paths simultaneously! This creates a dual-critical-path situation where delays on activities in either path will delay the project. Float for all activities on both paths = 0.
**Why not A:** 5 days represents only Activity E's duration, not an entire path through the network. The critical path must include a complete path from project start to project finish, and all activities on a path must be included in the duration calculation.
**Why not B:** While Path A-B-C does equal 12 days, this answer implies it is the only critical path. In this scenario, Path D-E also equals 12 days, meaning both paths are critical simultaneously. Identifying only one path as critical misses the dual-critical-path condition.
**Why not D:** 7 days represents only Activity D's duration, which is one activity on Path 2. The full Path D-E duration is 7 + 5 = 12 days. Individual activity durations do not represent complete path durations through the network.
Key Concept
This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).