CAPM Practice: Demonstrate an understanding of a project management plan schedule
Question 71 of 85 in Demonstrate an understanding of a project management plan schedule
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: An external constraint that must be incorporated into the project schedule
Explanation
A contractually imposed deadline is an external constraint — a hard requirement from outside the project that the schedule must accommodate. Unlike discretionary dependencies (which are based on team preference and can be adjusted), external constraints from contracts or regulations are non-negotiable and must be built into the project plan from the beginning.
**Why not B:** A contractually imposed deadline is not a discretionary dependency. Discretionary dependencies are based on team preference or best practice and can be adjusted. A client contract deadline is a hard, non-negotiable external constraint that the project must accommodate.
**Why not C:** While there may be uncertainty about whether the deadline is achievable, the deadline itself is a constraint, not an assumption. Assumptions are factors believed to be true for planning purposes. A contractual deadline is a documented, binding requirement — not something that "may or may not" apply.
**Why not D:** While the deadline could theoretically change through contract renegotiation, it is classified as a constraint, not a risk. A risk is an uncertain event that may occur. The deadline is a known, documented obligation that must be incorporated into the schedule as a hard constraint.
Key Concept
This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).