CAPM Practice: Demonstrate an understanding of a project management plan schedule
Question 71 of 85 in Demonstrate an understanding of a project management plan schedule
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: An external constraint that must be incorporated into the project schedule
Explanation
A contractually imposed deadline is an external constraint — a hard requirement from outside the project that the schedule must accommodate. Unlike discretionary constraints (which can be adjusted), external constraints from contracts or regulations are non-negotiable and must be built into the project plan from the beginning.
**Why not B:** A contractually imposed deadline is not a discretionary dependency. Discretionary dependencies are based on team preference or best practice and can be adjusted. A client contract deadline is a hard, non-negotiable external constraint that the project must accommodate.
**Why not C:** While there may be uncertainty about whether the deadline is achievable, the deadline itself is a constraint, not an assumption. Assumptions are factors believed to be true for planning purposes. A contractual deadline is a documented, binding requirement — not something that "may or may not" apply.
**Why not D:** While the deadline could theoretically change through contract renegotiation, it is classified as a constraint, not a risk. A risk is an uncertain event that may occur. The deadline is a known, documented obligation that must be incorporated into the schedule as a hard constraint.
Key Concept
This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).