CAPM Practice: Demonstrate an understanding of a project management plan schedule
A project manager is updating the project schedule after a two-week delay caused by a material delivery. The delay affected only non-critical activities, all of which had at least 3 weeks of float. What is the CORRECT assessment and action?
Key Concept
This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).