CAPM Practice: Demonstrate an understanding of a project management plan schedule
Question 29 of 85 in Demonstrate an understanding of a project management plan schedule
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Schedule Performance Index (SPI) used to forecast the Estimate to Complete for schedule
Explanation
The SPI can be used to forecast whether the project will finish on time. If SPI = 0.80, the project is performing at 80% schedule efficiency. Applying this to remaining work suggests it will take more calendar time than originally planned. For example: if 6 months remain planned, at SPI=0.80, it may take 6/0.80 = 7.5 months — forecasting a 1.5-month overrun.
**Why not A:** The Cost Performance Index (CPI) measures cost efficiency (EV/AC), not schedule performance. While CPI is valuable for forecasting cost overruns, it does not predict whether the project will finish on time — that requires the schedule-focused SPI metric.
**Why not B:** Schedule Variance (SV = EV - PV) shows the current difference between earned and planned value, indicating whether the project is ahead or behind at a point in time. However, SV alone does not forecast future completion — SPI provides the efficiency rate needed to project remaining duration.
**Why not C:** Comparing BAC to current spend compares the total budget to money spent, which is a crude cost measure that tells nothing about schedule performance. It does not account for the value of work actually completed and cannot predict whether the project will finish on time.
Key Concept
This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free